Pump Solutions for Combined Cycle Plants Quality Parts and Repair
Expedited Repair for Vertical Circulator Pump A 620MW combined cycle power plant located in the Southwest US was being sold.

Expedited Repair for Vertical Circulator Pump
A 620MW combined cycle power plant located in the Southwest US was being sold. Per the plant sale agreement, all equipment needed to operate at optimum levels prior to the sale closure at the end of the year.
The plant contacted Hydro and requested a rapid repair of one of their vertical circulating pumps. The pump had been installed in 2001 and showed progressive signs of degradation. The vertical circulating pump was rated for 87,000 GPM at 87’ TDH and pumped cooling tower water.
To meet the sale agreement, the pump needed to be removed, repaired, and returned by the end of the year.
Hydro was commissioned to pull the pump and prepare it for shipment to Hydro’s service center in Houston, TX. Hydro’s Field Service group was staged and immediately dispatched to facilitate removal of the pump unit.
Preliminary Analysis
When the unit arrived in Texas, it was disassembled and inspected on an expedited basis. Several remedial actions were quickly identified. Parts, such as sleeve bushings, needed to be replaced. Weld repairs and machining were recommended for out-of-tolerance components. The shaft needed to be repaired and the total indicated runout brought within acceptable limits.
The most dramatic issue identified was damage to the impeller, which was severely worn with large holes in each of the five vanes. Engineers and coating specialists evaluated the efficacy of repairing the impeller by applying epoxy coating to fill the voids in the impeller vanes. This process was determined to be insufficient and could not be guaranteed after repair.
It was estimated that the repairs stated for all other components could be accomplished in a relatively short period of time. However, the best delivery quoted by the OEM for a new impeller was 16-20 weeks.
Replacement Impeller Solution
In light of the long lead time quoted by the OEM, other resources had to be engaged to provide an impeller in the accelerated schedule required by the customer. Hydro Parts Solutions (HPS) was called in to engineer and manufacture a replacement impeller in an expedited time frame. HPS immediately visited the Houston service center to reverse engineer the impeller using state-of-the-art tools and technology that provide a full dimensional analysis. Anticipated delivery for the new impeller was estimated at 8-10 weeks, half of what the OEM originally quoted.
While the impeller was manufactured by HPS, repairs proceeded on the other pump components at Hydro’s Texas service center. The new impeller was reverse engineered, cast, machined, inspected, and delivered within eight weeks of the work release. The final product was scanned using the coordinate measuring machine and this scan was mapped onto the the original dimensional analysis to ensure conformity to the original design.
The pump was assembled and prepared for shipment within nine weeks of its release to manufacturing. Hydro’s Field Service group was again deployed to reinstall the pump onsite as soon as the refurbishment was completed.
Close-up of damaged impellerBetter Than New in a Fraction of the Time
In many cases, ordering a replacement part to original specifications through the OEM is subject to significant backlog times. Hydro Parts Solutions is able to cast parts of the highest quality, within a much shorter lead time.
Hydro has engineered hundreds of combined cycle pump repairs and upgrades. Our exacting tolerances and assembly procedures are often more stringent than those originally provided by the OEM, resulting in a more rugged, reliable pump.
Machining of new impellerHydro’s full breadth of services – including field services, repairs, engineering and parts solutions – provides customers with the highest quality pump solutions in reasonable time frames.